AC | Actual Cost |
ACWP | Actual Cost of Work Performed |
AD | Activity Description |
ADM | Arrow Diagramming Method |
AE | Apportioned Effort |
AF | Actual Finish |
AOA | Activity – On – Arrow |
AON | Activity – On – Node |
AS | Actual Start |
BAC | Budget At Completion |
BCWP | Budgeted Cost of Work Performed |
BCWS | Budgeted Cost of Work Scheduled |
BOM | Bill Of Materials |
CA | Control Account |
CAP | Control Account Plan |
CCB | Change Control Board |
COE | Center of Excellance |
COQ | Cost Of Quality |
CPAF | Cost plus award fee |
CPF | Cost-Plus-Fee |
CPFF | Cost-Plus-Fixed-Fee |
CPI | Cost Performance Index |
CPIF | Cost-Plus-Incentive-Fee |
CPM | Critical Path Method |
CPPC | Cost-Plus-Percentage of Cost |
CV | Cost Variance |
CWBS | Contract Work Breakdown Structure |
DD | Data Date |
DU | Duration |
DUR | Duration |
EAC | Estimate at Completion |
EF | Early Finish Date |
EMV | Expected Monetary Value |
ES | Early Start Date |
ETC | Estimate to Complete |
EV | Earned Value |
EVM | Earned Valued Management |
EVT | Earned Valued Technique |
FF | Finish-to-Finish |
FF | Free Float |
FFP | Firm-Fixed-Price |
FMEA | Failure Mode and Effect Analysis |
FPIF | Fixed-Price-Incentive-Fee |
FS | Finish-to-Start |
IFB | Invitation for Bid |
KPI | Key Performance Indicator |
LF | Late Finish date |
LOE | Level of Effort |
LS | Late Start date |
MOP | Method Of Procedure |
OBS | Organizational Breakdown Structure |
OD | Original Duration |
PC | Percent Complete |
PCT | Percent Complete |
PDM | Precedence Diagramming Method |
PF | Planned Finish date |
PM | Project Management |
PM | Project Manager |
PMBOK | Project Management Body Of Knowledge |
PMIS | Project Management Institute |
PMIS | Project Management Information System |
PMO | Program Management Office |
PMP | Project Management Professional |
PS | Planned Start Date |
PSWBS | Project Summary Work Breakdown Structure |
PV | Planned Value |
QA | Quality Assurance |
QC | Quality Control |
QFD | Quality Function Deployment |
RACI | Responsible, Accountable, Consult, Inform (Matrix) |
RAM | Responsibility Assignment Matrix |
RBS | Resource Breakdown Structure |
RBS | Risk Breakdown Structure |
RD | Remaining Duration |
RFI | Request for information |
RFP | Request for Proposal |
RFQ | Request for Quotation |
SF | Scheduled Finish |
SF | Start-to-Finish |
SOP | Standard Operating Procedure |
SOW | Statement of Work |
SPI | Scheduled Performance Index |
SS | Scheduled Start |
SS | Start-to-Start |
SV | Schedule Variance |
SWAG | Sophisticated Wild Ass Guess |
SWOT | Strenths, Weaknees, Oppurtunities, and Threads |
TC | Target Completion date |
TF | Target Finish date |
TF | Total Float |
T&M | Time and Material |
TQM | Total Quality Management |
TS | Target Start date |
VE | Value Engineering |
WBS | Work Breakdown Structure |